Dix has just completed manufacture and installation of stainless steel 316 pipework and fine bubble diffuser skids for the Kangaroo Valley Sewerage Scheme. We worked within a tight timeline and also had to tackle several issues " on the fly " to accommodate last minute design changes by our client.

Our engineers also made several recommendations such as alternative types of anchors, width changes to the skid frames to reduce frame packing requirements, plus using Victaulic couplings instead of flanges to reduce problems during installation, and make transportation of the pipe-work to site easier.

KVSS pipe-work3

Blower air pipes awaiting installation of Blowers

KVSS pipe-work 4

Fine Bubble Diffuser skid (1of4) in bottom of 5m deep tank. Siemens to install diffuser caps.

Skid is removable for maintenance and guided by four 100mm x 100mm SS316 angles secured to the wall.

KVSS pipe-work5

Photo showing pipe-work to train 2 coming from the blower room to the basin tanks.

Train 1 is a mirror image on the eastern side.